Received
Notice to Proceed |
March
28, 2003 |
| |
Preliminary
Engineering Investigation |
March
2003 - May 2003 |
| |
Public
Involvement |
March
2003 - December 2003 |
| |
Public
Scoping Meeting Number One |
May
21, 2003 |
| |
Traffic
Operation and Safety Analysis |
November
10, 2003 |
| |
Draft
Design Study Report - Phase 1 |
April
2004 |
| |
Public
Meeting Number Two |
June
21, 2004 |
| |
Final
Design Study Report - Phase 1 |
July
2004 |
| |
Right-of-Way
Acquisition |
May
2004 - July 2005 |
| |
Design
- Phase 1 |
August
2004 - July 2005 |
| |
Bidding
- Phase 1 |
November
2005 - December 2005 |
| |
Construction
- Phase 1 |
May
2006 - August 2007 |
| |
Phase
II Construction |
June
2008 - July 2008 |
| |
Phase
III Design and Utilities |
2008
- 2009 |
| |
Phase
III Construction |
2010
- 2011 |