| Agency Scoping Meeting | October 19, 2006 |
| Public Scoping Meeting | October 23, 2006 |
| Reconnaissance Report | Spring 2007 |
| Public Meeting Number Two | April 5, 2007 |
| Public Meeting Number Three | July 12, 2007 |
| Public Meeting Number Three | February 23, 2009 |
| Public Meeting Number Four | October 29, 2008 |
| CAMP Phase 1 | Spring 2009 |
| CAMP Phase 2 | Summer/Fall 2009 |
| Environmental Document | Winter 2009 |
| Final Roadway Design | Spring 2010 |
| ROW Acquisition | Fall 2008-Spring 2010 |
| Construction | 2010 |
|