Project Phases and Schedule
   
  Project Scoping Spring 2006
  Preliminary Engineering Report and Design Study Jan. through September 2006
  Environmental Documentation & Permitting Spring 2007 through Spring 2008
  Engineering Design June 2007 through January 2009
  Bid Ready Fall 2009
  Construction Summer 2010