Schedule
|
Public Meeting Held
|
November 6, 2008
|
|
Preliminary Design
|
November 2008 - March 2009
|
| Detailed Design |
March 2009 - November 2009 |
|
Environmental Permits |
January 2009 - November
2009 |
|
ROW Acquisition |
January 2009 - December
2009 |
|
ROW Neighborhood Meeting Held |
April 28, 2009 |
|
Public Meeting #2 Held |
June 18, 2009 |
|
Utility Relocation and Building Demolition |
Summer 2010 |
|
Road Construction |
Summer 2011 |
|
|
|
|
|